Tile Roof Replacement & Design
Because everyone’s home and needs are different, build the roof system that is right for you, customized with exclusive features to fit your home for enhanced performance.
Process
Tile Roofs offer beauty and protection against harsh elements. Eastman
Roofing and Waterproofing, Inc. has designed a complete system with
"code-plus" options that outperform other specifications, utilizing the
best and newest technologies with proven roofing practices. The
complete "system" components work together to form long-lasting,
worry-free security.
Steps
1. Tear off and haul away the roof system, including plumber’s flashings and vents. Remove or hammer nails flush with sheeting/roof deck. | ||
2. Inspect entire roof area for dry rot damage in roof deck and replace with new. | ||
3. Inspect entire edge perimeter for dry rot in fascia boards and barge rafters and replace with new. | ||
4. (a)Solid
Sheeting 1)
Reanchor any roof deck nails that have popped up; 2) Reanchor per American
Plywood Association specifications for shear strength; 3) Reanchor per American
Plywood Association specification for shear strength with ring shank nails in high
wind areas (Eastman Roofing & Waterproofing recommends following the
American Plywood Association guidelines. If you are in a windy area, we
recommend ring shank nails). *Options to Decide |
||
4. (b)Space Sheeting Install OSB, OSB with Radiant Barrier or CDX plywood over existing space sheeting, or existing solid sheeting. 1) Install 4’ x 8’ sheets as a backing only for the new roof; 2) Install 4’ x 8’ sheets per American Plywood Association specifications for ‘shear’; 3) Install 4’ x 8’ sheets per American Plywood Association specifications for shear with ring shank nails, ‘high wind areas’. *Options to Decide |
||
5. Install Roofer’s Select underlayment to entire roof area, WinterGuard self-adhered modified rubber leak barrier to valleys, roof penetrations, and low slope areas. *Options to Decide |
||
6. Install new modified rubber flat roof membrane at low slope and tie into tile roof above. | ||
7. Install flashings in underlayment to double flash roof penetrations. | ||
8. Install new VELUX self-flashed, all-in-one, leak proof tempered glass skylight(s) over existing opening(s), where applicable, fastened and sealed. | ||
9. Install new valley metal with hem and fasten where applicable. | ||
10. Install eave riser or bird stop at eave edge. | ||
11. Install new plumber’s flashings over plumbing stacks and new vents over exhaust areas; weave into tile roof. | ||
12. Paint all plumber’s flashings and vents to match tile color, where applicable. | ||
13. Install new electric powered attic ventilator with thermostat control for proper attic ventilation, fastened and sealed, where applicable. | ||
14. Install batts at proper spacing for tile and batt extensions at valleys. | ||
15. Install tile to the entire roof area, fastened with copper nails. | ||
16. Clean up and remove all debris. Use magnet to remove fasteners from lawn. | ||
17. 10 Year warranty on all work performed by Eastman Roofing & Waterproofing. | ||
18. Guarantee on tile underlayment from manufacturer specs, 50 years. | ||
19. Fifty year warranty on tile from the manufacturer. |